In this aerial photograph, the aircraft carrier John F. Kennedy (CVN-79) sits at Pier 3 at Newport News Shipbuilding division. The ship is approximately 76 percent complete and is progressing through final outfitting and testing. Huntington Ingalls Industries photo.
USNI News: Ford Aircraft Carrier John F. Kennedy to Deliver a Year Later
The next Ford-class aircraft carrier will now deliver to the Navy in 2025, one year later than the service’s most recent projection, according to Fiscal Year 2024 budget documents released this week.
The Navy delayed future carrier John F. Kennedy’s (CVN-79) delivery date from June 2024 so the service could alter the ship’s Post Shakedown Availability (PSA) and perform more work during construction, according to the service’s Fiscal Year 2024 budget documents.
“The Navy is implementing a strategy to pull baseline work from the Post Shakedown Availability (PSA) into the construction period in order to provide more capability at ship delivery,” the Navy’s shipbuilding budget books read.
Read more ....
WNU Editor: The Pentagon is spending the money .... Pentagon budget 2024: US Navy requests USD3.9 billion for major aircraft carrier work (Janes).
2 comments:
What's the cost of a Kinzhal?
2025 delivery date?
Based on the USS Ford experience....
Don't hold your breath.
Post a Comment